ShuoStarSourcing & Trading, home

Guide

Buying municipal Christmas decorations: the RFP, the spec and the order date

A city buys holiday decorations on a public calendar, and imported decorations run on a factory's. This guide covers when to start, what to put in the specification and the price schedule so bids compare, and wording you can adapt.

Routes

Three ways a city buys holiday decorations

A snowy main street at dusk with lit snowflake decorations on the lamp posts and a garland arch across the road

Which route you are on decides what you write, who places the order with a factory, and who owns the decorations in January.

  • Buy them outright

    The city writes a specification, issues an RFP or a bid, and owns what it buys. The winning bidder supplies the goods and sometimes installs them.

  • Buy through a cooperative programme

    Some public agencies buy through cooperative purchasing programmes, where another agency has already run the solicitation. Suppliers say which programmes they are on.

  • Hire a decor contractor

    The contractor designs, installs, removes and often stores the decorations, and usually owns them. The factory order is then the contractor's, on the same calendar.

Timing

When to start: the calendar for imported decorations

The calendar works back from the install date through production, the ocean and rail legs, the customs entry and a buffer. It uses custom displays, the longest chain we quote.

Holiday lighting tenders go out from late winter into summer. This year we saw cities post them in March, May and July. For imported custom pieces, the award has to come before the factory can book production, and we plan on 8 to 12 weeks to produce custom steel and lighting work. After that the container crosses the ocean, often with a rail leg inland, and clears customs before the install crew starts.

If you buy through a procurement process, put its length in front of the order date. A tender that closes in late spring and awards in June can still make a November install, but only if the drawings are approved quickly after the award.

Needed on site by

Order by, to be safe

May 3, 2027

Every stage at its slowest planned duration: 196 days.

Latest possible, if everything runs fast

Jul 25, 2027

106 days, plus 7 days of planning time for China's National Day holiday if every stage runs at its fastest. Do not plan on it.

  1. Drawing approval, deposit and factory booking

    Planning allowance. Custom work needs an approved drawing before a slot is booked.

    7 to 14 daysMay 3, 2027 to May 17, 2027modelled
  2. Production

    Planning allowance for custom steel and lighting work. The real window for your drawing is confirmed on the quote once the drawing is approved.

    56 to 84 daysMay 17, 2027 to Aug 9, 2027modelled
  3. Inland to port, export clearance, vessel cut-off

    Planning allowance from the factory to the sailing port.

    5 to 10 daysAug 9, 2027 to Aug 19, 2027modelled
  4. Ocean transit, Yantian to Chicago, 40ft

    Freightos via our freight-rate pipeline, captured 2026-09-03. Range covers every routing offered on the lane that day.

    23 to 66 daysAug 19, 2027 to Oct 24, 2027provider
  5. Customs entry, drayage and delivery

    Planning allowance. Our broker files the entry. A customs exam adds time that nobody controls.

    5 to 12 daysOct 24, 2027 to Nov 5, 2027modelled
  6. On-site buffer before opening

    So a late container does not become a late opening.

    10 daysNov 5, 2027 to Nov 15, 2027modelled

Ocean transit from our own freight-rate pipeline (Freightos), snapshot 2026-09-03. Production window and allowances are planning estimates; the quote is the commitment. The stages in China leave room for Chinese New Year and China's National Day holiday in October, but each factory sets its own holiday dates. Municipal buyers: add your own procurement lead time in front of the order date.

Not ready for a quote yet?

Get these dates by email. They arrive straight away, and you can reply to them when you are ready.

Used only to answer this. Privacy notice

For your own dates, work the order date back from the install month on the buying calendar.

Specification

Write the specification: performance, not pictures

Describe what each piece has to do and where it goes. Bidders can price a requirement; they cannot price a mood board.

Bid documents with line drawings of lamp-post decorations on a table, with a C9 bulb, a pole bracket and a length of garland
  • A schedule of assets and locations

    Each piece on its own line: what it is, how many, and where it goes. A photo of each location helps bidders more than a paragraph about the theme.

  • Size and viewing sides

    Height and width, and whether each piece is seen from one side, from both sides of a street, or from all round.

  • How each piece mounts

    For pole mounts, give bidders blanks to fill rather than leaving them to guess: pole height and diameter, the bracket or banner arm already on the pole, and whether there is power at the pole. For ground pieces, say what they stand on.

  • Colour and animation

    Warm or cool white, any colours, steady or animated. If pieces must match decorations the city already owns, send photos of those.

  • Power and control

    Ask each bidder to state the power and control each structure needs, so the city can check it against what each site has.

  • Weather

    If a location is exposed, state the conditions the pieces must stand up to and ask bidders how their design meets them.

  • Packing and spares

    Frames that knock down, crates with the assembly drawing inside, and a list of spare parts to hold for later seasons.

Price schedule

A price schedule that makes bids comparable

Give bidders a schedule with one line per cost. Two bids can then be read side by side instead of total against total.

LineWhat it coversWhy it gets its own line
Design and drawingsDimensioned drawings for the city to approve before productionSome bidders fold design into the goods and some charge for it; a separate line shows which.
GoodsEach piece on the asset schedule, priced per unitIt is the line most bids agree on, and a single total can hide everything else behind it.
Freight and deliveryFactory to the city's yard or site, by container and truckImported decorations carry ocean freight that a bare unit price leaves out.
Customs entry and dutyThe broker's entry, the tariff line and the dutyDuty on imported lighting and steel moves with tariff policy. A named line makes a change visible.
Installation and removalCrew, lifts and permits, each seasonOften a different contractor. Pricing it apart lets the city award it apart.
StorageWhere the decorations live from January to OctoberIt is a cost every year, and some tenders require storage off site.
Maintenance and sparesRepairs in season and a stock of spare partsFailures happen in December, when replacements are hardest to get.

On the duty line, ask each bidder for the tariff line they priced against, the rate, and who carries a change between the award and the day the container lands. Our quotes state all three. To compare bids on landed cost, put each bid's lines into the calculator.

Imported goods

Origin, duty and the tariff line in the bid

Ask every bidder where each item is made. A bidder reselling imported goods and one building locally can both answer honestly, and the answer changes the lead time, the duty and what happens if a piece fails in December.

Duty is charged at the rate in force on the day of entry, not the day of the bid. On a tender awarded in June and landed in October, that gap is months long. Say in the solicitation who carries a change in duty over that gap, so every bidder prices the same risk.

If a domestic-preference rule applies to your contract, the solicitation has to say so. Whether one applies is a question for your procurement office or counsel. A bidder who cannot meet it should say so in the bid, not after the award.

Our own answers are on How we work: which company invoices you, and who carries a tariff change. Shipping and duties explains what the freight, entry and duty lines of a landed quote cover.

Evaluation

Scoring the bids

A grid the city can adapt. The emphasis column is an example; the city sets its own weights.

CriterionWhat to look forExample emphasis
PriceThe total from the price schedule, with every line filled inHigh
Delivery against the install dateA dated plan from award to install, with production and transit shownHigh
Match to the specificationDrawings that meet the asset schedule and the mounting blanksHigh
Service in seasonWho answers a failure in December, and howMedium
QualificationsDrawings of similar work, insurance and references, in the form the city's rules requireMedium

References, insurance and bonding are the city's requirements to set. Ask for them in the solicitation rather than assuming every bidder holds them.

Later seasons

After the award: storage, upkeep and the next season

Commercial decorations are bought to last several seasons, so settle before the first install who stores them, where, and with what inventory. A tender that requires off-site storage should say so, because it changes who can bid.

Keep the approved drawings. Reorders and replacement pieces are quoted from the drawing on file, so a piece added in the third year matches the ones bought in the first. Spare bulbs are worth holding as well: C9 bulbs and socket wire for trees and rooflines are ordered by the pallet or the container.

Used commercial decorations also come up for sale. Before buying, check the frames for rust and cracked welds, test the lighting, and ask for the drawings, since spare parts and matching pieces are made from them.

Sample wording

Clause wording you can adapt

Sample wording, not legal advice. Your procurement office or counsel fits it to your rules.

  • Scope

    "The contractor shall supply the decorations listed in Schedule A, built to the approved drawings and delivered to the locations in Schedule B by [date]."

  • Origin

    "For each item, the bidder shall state the country in which it is manufactured."

  • Tariff line and duty

    "For each imported item, the bidder shall state the tariff classification and the duty rate used in its price, and whether the bidder or the city carries any change in duty before delivery."

  • Drawing approval

    "Production shall not start until the city has approved dimensioned drawings showing the front, back and base of each structure, with its mounting and power."

  • Test before shipment

    "Each lit structure shall be tested before packing, and photographs of the test shall be supplied to the city before shipment."

  • Packing

    "Each structure shall ship knocked down where its design allows, with its assembly drawing packed inside its crate."

Where we fit

What we can supply into a solicitation

We are a trading company. We have decorations made in China and deliver them landed, to a city or to the contractor it hires.

  • Goods to the city's specification

    Pole-mount motifs and street displays built to drawing, giant wreaths and garland for building fronts, and C9 bulbs and socket wire for trees and rooflines.

  • Dimensioned drawings

    Drawings for the city to approve before production, showing the front, back, base, mounting and power.

  • A landed quote

    Goods, freight, the entry and the duty line itemised, with the tariff line, the rate and who carries a change.

  • The invoice a public agency needs

    If you are a public agency and need to pay a US vendor, say so in your request and we will quote from our US company.

  • What we do not do

    We do not install, maintain or store decorations on site, and we are not on a cooperative purchasing programme. A contractor who installs can buy from us.

Questions

Questions buyers ask

Where can a city buy used commercial Christmas decorations?

Used commercial decorations do come up for sale. Before buying, check the frames for rust and cracked welds, test the lighting, and ask for the drawings, because spare parts and matching pieces are made from them.

How do you decorate a light pole for Christmas?

With a pole-mount motif: a lit frame fixed to the pole with a bracket or the banner arm already on it. To buy them in quantity, measure the pole height and diameter, note the bracket and whether there is power at the pole, and put those in the specification. The pole-mount decorations page covers the mount and the motif.

What are lit Christmas decorations for streets called?

In the trade they are motifs: lit steel frames, flat or 3D. On streets they are usually pole-mount motifs on lamp posts, garland or overhead pieces across the road, and larger figures in squares and parks.

Does a city need an RFP to buy holiday decorations?

It depends on the city's purchasing rules and the size of the purchase. Smaller purchases can often be made on quotes, and some agencies buy through cooperative purchasing programmes that have already run a solicitation. Your procurement office sets the thresholds.

How far ahead should a city order imported holiday decorations?

Work back from the install date: production (we plan on 8 to 12 weeks for custom steel and lighting work), the ocean and rail legs, the entry, and a buffer before install. For a November install that puts the award in early summer and the RFP in spring. The buying calendar does the arithmetic for any date.

Who owns and stores the decorations under a decorating contract?

Under a turnkey decor contract the contractor usually owns the decorations, installs and removes them, and stores them between seasons. If the city buys outright, it owns them and has to plan the storage. Say which you want in the solicitation.

Request a quote

A landed quote for your city's decorations

Send the asset schedule or a sketch, the quantities and the install date. We reply within 1 business day, and the quote itemises the goods, the freight, the entry and the duty line.

  • Reply within 1 business day
  • Landed cost, itemised

Request a quote

We take on the orders we can do well, and we will say so if yours isn't one of them.

A loaded container ship at sea at dusk, seen from above